Lesson 2 of 5 · 14 min

Base rates and the outside view

Why projects almost always take longer than planned, and how comparing with similar cases helps fix that.

Imagine you are planning the roll-out of a new information system. The team builds a step-by-step schedule, estimates each step sensibly and arrives at: six months. Everyone nods.

This approach – estimating from inside the project, from its specific steps – is what psychologist Daniel Kahneman called the inside view. It is natural, detailed and convincing. And it consistently leads to optimistic estimates.

The planning fallacy

Kahneman and Amos Tversky described the tendency to underestimate the time, costs and risks of our own plans and to overestimate their benefits. They called it the planning fallacy. What makes it treacherous is that it affects even people who know their past projects ran late. Every new project feels special, and we can't yet picture its problems.

The inside view accounts for the plan, but not for what never appears in the plan: a key person falling ill, a change of scope, approval delays, technical surprises. Each of these is unlikely on its own, but the probability that none of them happens is small.

Base rates

A base rate tells you how things usually turn out in a group of similar cases. How many similar IT projects finish on time? What share of new restaurants in your city survive their first three years? How long does it usually take your organisation to fill a senior role?

The base rate is the anchor an estimate should start from. Yet people often ignore it, because a specific story (“our team is experienced, we have a great plan”) is far more vivid than a dry statistic.

The outside view: reference class forecasting

Kahneman recommended complementing the inside view with the outside view. The economic geographer Bent Flyvbjerg developed it into a practical method for large infrastructure projects under the name reference class forecasting. It has three steps:

  1. Find a reference class. A group of sufficiently similar projects you have data on – your own past projects, industry data, experience of peers in other organisations.
  2. Look at the distribution of outcomes. How long these projects took, what they cost, what share ran late and by how much.
  3. Adjust for specifics. Only now consider how your project genuinely differs – and be sceptical of these adjustments. Everyone has told themselves “this time it's different”.

Things to watch out for

  • The reference class doesn't have to be perfect. Even a rough comparison with five similar cases is usually better than none.
  • Beware of picking only successes. If you only look at projects people talk about because they went well, the base rate will be too optimistic.
  • Add specifics with care. Every project has something unique. The question is whether it really changes the odds or just the story.
  • It applies to benefits too. The outside view isn't only for deadlines and costs, but also for estimates of revenue, savings and the impact of changes.

Check your understanding

Quiz · 0/3
  1. 1. What is the “inside view”?

  2. 2. You plan to open a new branch. What is the best first step in estimating how long it will take to become profitable?

  3. 3. Why does the planning fallacy affect even experienced managers who know projects run late?

Found a mistake or inaccuracy in this lesson?Report a mistake

What next

Done? Next lesson: Pre-mortem and devil's advocate (14 min)